HYGIENIC 2 FINAL

Major VersionM

by Jason Wiseman

  1. Gather all components needed to assemble the Hygienic 2.
    • Gather all components needed to assemble the Hygienic 2.

    • Click here to see an exploded view and parts list of the Hygienic 2.

    • Slide Horizontal Shaft 75-1844S through Nozzle Carrier Assembly.

    • Use 5/32" Hex Bit to Finger tighten Horizontal Shaft 75-1844S to Elbow 75-1859S.

    • Apply anti-seize to threads.

    • Place Elbow 75-1859S in a soft jawed vice and torque Horizontal Shaft 75-1844S to 20 in-lbs.

    • Install Roll Pin 75-1856 into one of the holes at lower end of Body 75-1853S.

    • Install Bevel Gear 75-1852 to Roll Pin on body by aligning holes.

    • Install Retaining Ring 75-1855 to groove on Body located just above Bevel Gear 75-1852.

    • Use the 1-1/8" deep socket, to Install Vertical Shaft 75-1854 to Elbow 75-1859S. Torque to 20 ft-lbs.

    • Install Rotor 75-1801-SS to Vertical Shaft 75-1854 using a flat wrench.

    • Apply anti-seize to rotor.

    • Tighten snugly.

    • Seat motor 75-1857 inside body.

    • Install the o-ring onto the 75-1403S Inlet Cap

    • Install the Inlet Cap to the 75-1853S Body.

    • Apply anti-seize to OD thread of inlet cap.

    • Use Molykote 111 or equivalent product to lubricate the O-ring.

    • Clamp onto flats of Body 75-1853S and tighten Inlet Cap 75-1403S to 60 ft-lbs.

    • Do not use excessive force when clamping.

    • Install Nozzles 75-1849 nozzles and tighten to 15 ft lbs.

    • The Hygienic 2 is complete.

Finish Line

One other person completed this guide.

Daniel Weeks

Member since: 07/27/2016

4,153 Reputation

10 Guides authored

0 Comments

Add Comment

View Statistics:

Past 24 Hours: 0

Past 7 Days: 0

Past 30 Days: 2

All Time: 183